Construction on both sides of railway line approved
Jaipur: In a news related to Civil Lines Railway Overbridge, approval has been received for construction on both sides of the railway line. The Railway approved the design sent by the Jaipur Development Authority.
Now, the JDA will soon start work on both sides of the railway line. Piling work will be started on both sides. Before this, the height barrier will be removed. The work had got stuck as the railways had not approved it.
The piling work was stuck for the last six months. The deadline for completion of the project is August 11. Now, it seems that the work will be completed on time.
It is noteworthy that ROB is planned on the Jaipur-Delhi and JaipurSawai Madhopur railway lines to ease traffic woes. Due to closure of railway overbridge, traffic coming from Jacob Road, Jamnalal Bajaj Marg, Transport Road, and Sawai Pratap Marg gets congested from more than 1.3 million TVUs.